. A, B and C can complete a work in 10, 12 and 15 days respectively. All three of them starts together but
after 2 days A leaves the job and B left the job 3 days before the work was completed. C completed the
remaining work alone. In how many days was the total work completed?
Answers
Step-by-step explanation:
A left after working 2days,
B leaves 3 days before completion of work----(x-3)
2/10+(x-3)/12+x/15=1
LCM of 10,12,15 is 60
6×2+5(x-3)+4x=60
12+5x-15+4x=60
9x-3=60
9x=60+3
x=63/9
x=7
Total work completed in 7 days
In 7 days, the total work was completed
Solution:
Given that,
A, B and C can complete a work in 10, 12 and 15 days respectively
Given that,
After 2 days, A leaves the job
So, A worked for 2 days alone
Let "x" be the days in which total work was completed
B left the job 3 days before the work was completed
Therefore,
B worked for (x - 3) days
C completed the remaining work alone
Thus C worked for "x" days
Therefore,
Thus, in 7 days, the total work was completed
Learn more about this topic
A, b and c each of them working alone can complete a job in 10, 12 and 15 days respectively. if all three of them work together to complete a job and earn rs. 6000, what will be c's share of the earnings?
https://brainly.in/question/1260399
If x y z can do a work in 10 12 15 days respectively then x y z together can do the same work in
https://brainly.in/question/4385682