A, B and C can complete a work in 12, 24, 36 days respectively. In how many days will they together complete the work​

Attachments:

Answers

Answered by singhrajputpalak6
2

Step-by-step explanation:

A does (1/12)th of the work in a day.

B does (1/24)th of the work in a day.

C does (1/36)th of the work in a day.

A, B and C working together for 'x' days to complete a work.

As you know, time xcapacity=work

so, 'x' days x total capacity=work

Mathematically,

Xx{1/12 + 1/24 + 1/36}=1 (right hand side, 1 show a single work has to do).

Xx{11/72} = 1

X = 72/11 days.