Math, asked by pravinsharma368, 10 months ago


A, B and C can complete a work in 2 h. If A does the job alone in 6 h and B in 5 h, how long will it take for
Cto finish the job alone?​

Answers

Answered by VinilM
1

Answer:

Step-by-step explanation:

7.5 hours