A, B and C can complete a work in 20, 24 and 30 days respectively. All three of them starts together but after 4 days A leaves the job and B left the job 6days before the work was completed. C completed the remaining work alone. In how many days was the total work completed?
A) 10 B) 12 C) 14 D) 16
Answers
Answered by
1
Answer:
B)12
hope it helps you
mark me as brainliest
Step-by-step explanation:
follow me and inbox me
Answered by
0
Answer:
your answer is B 12 please follow me