A, B and C can complete a work in 4 days, if A alone can complete a work in 12 days, B alone can complete a work in 18 days, in how many days C alone can complete a same work?
Answers
Answered by
1
Answer:
9 days
Step-by-step explanation:
1/4 = 1/12+ 1/18 +1/x
1/4 - 5/36 = 1/x
1/x = 4/36 =1/9
x = 9 days