A, B and C can complete a work in 5 days. If A and C can complete the same work in 7 1/2 days and A alone in 15 days, then in how many days can B and C finish the work?
Answers
Answered by
3
Answer:
B and C can do work in 15/2
Step-by-step explanation:
please check the image
Attachments:
Answered by
0
Answer:
B and C finish the work in 71/2 days.
Step-by-step explanation:
A+B+C complete the work in 5 days.
(A+B+C)'s 1 day work = 1/5
Best answer
(A + C) complete the work in 7 1/2 days = 15/2 days
(A+C)'s 1 day work = 1/15/22/15
B's 1 day work = (A+B+C)'s 1 day work - (A+ C)'s 1 day work.
1/5-2/15 3/15-2/15
C's 1 day work (A + C)'s 1 day work-A's 1 day work
=2/5-1/15 1/15
Now (A+C)'s 1 day work = B's 1 day work+ C's 1 day work
=1/15+1/15=2/15
(B+ C) can complete the work in 1/(2/15) days.
=15/2 days=71/2 days
B and C finish the work in 71/2 days.
#SPJ2