A,B and C can complete the job in 4 days, 5 days and 6 days respectively. They work together and complete it. If their total is wage is ₹3700,find A's wage​

Answers

Answered by piyushrai7800
2

Answer:

A= 4

B= 5

c= 6. LCM = 60

efficiency of

A = 60÷ 4= 15

B = 60 ÷5 =12

C = 60 ÷ 6 = 10

total wage = 3700

efficiency = 15+12 +10 = 37

3700÷ 37 = 100

15× 100 = 1500