Math, asked by gyan99176, 9 months ago

a b and c can do a job in 12h 20h and 30h respectively. if they all work together how long will they take to complete the job ? answer =6 days.
I WANT FULL CORRECT SOLUTION FOR IT . WHO S I LIKE I WILL FOLLOW HIM HER

Answers

Answered by harishbaland
29

Answer:

yes 6 hours is right answer

Step-by-step explanation:

A = 12 hours

B = 20 hours

C = 30 hours

let us consider that total work is = 60 unit (by lcm)

If total work is 60 unit and a can do it in 12 hours

means = 60/12 = 5 unit work per hour

similarly => B = 60/20 = 3 unit work per hour

=> C = 60/30 = 2 unit of work per hour

total work of one hour = 5+3+2 = 10 unit

now time taken = total work/efficiency

=> 60/10 = 6 hours