. A b and c can do a peice of work in 12 day 15 days, and 10 days respectively in what time
will they all together finishh it
Answers
Answered by
1
Step-by-step explanation:
A can do a piece of work in=12 days
Work done by A in 1 day=1/12
B can do a piece of work in =15 days
Work done by B in 1 day=1/15
C can do a piece of work in =10 days
Work done by C in 1 day=1/10
Work done by A,B and C together in 1 day=1/12+1/15+1/10
=1/4
Therefore time taken to complete the piece of work by A,B and C together=4 days