A,B and C can do a piece of work , A in 5 days , B in 8 days and C in 12 days . How long will they take to complete the work if they work together?
Answers
Answered by
0
Answer:
Step-by-step explanation:
A can do work in 5 days
⇒ A can do 1/5 th work in one day
B can do work in 8 days
⇒ B can do 1/8th work in one day
C can do work in 12 days
⇒ C can do 1/12th work in one day
A + B + C work in one day = 1/5 + 1/8 + 1/12
( LCM of 5,8 and 12 is 120 )
= 24 / 120 + 15 / 120 + 10 / 120
=( 24 + 15 + 10) / 120
= 49 / 120
A + B + C can finish work in 120/49 days
Answered by
0
Step-by-step explanation:
A in 5 days ,
A's one days work = 1/5
B in 8 days
B's one days work = 1/8
C in 12 days .
c's one days work= 1/12
A, B, C 's one days work= 1/5+1/8+1/12
= (24+15+10)/120=49/120
time taken to complete the work if they work together?= 120/49 days 2 22/49 days