A,B and C can do a piece of work in 10 days. A alone can do it in 40 days and B alone can do it in 30 days. In how many days will C alone can do the same work ?.
Answers
Answered by
0
Answer:
24 days
Step-by-step explanation:
A, B and C can do piece of work in 10 days
so they can do 1/10 part of work in a day
A alone can do same work in 40 days
so A can do 1/40 part of work in a day
B alone can do it in 30 days
so B can do 1/30 part of work in a day
let the days taken by C be x
1/10=1/40+1/30+1/x
1/10 7/120+1/x
1/10-7/120=1/x
12-7/120=1/x
5/120=1/x
1/24=1/x
therefore C can do 1/24 in a day
so C can do whole piece of work in 24 days