A B and C can do a piece of work in 10 days A alone do the work in 40 days and B alone do the work in 30 days in how many days c will do the work
Answers
Answered by
3
Step-by-step explanation:
Work done by A,B,C in 1d= 1/10
Work done by A in 1d= 1/40
Work done by B in 1d= 1/30
Work done by C in 1d= 1/10-(1/30+1/40)=5/120=1/24
So,C alone takes 24 days to finish the work