A,B and c can do a piece of work in 12days,15days and 10 days respectively. In what time will they all together finish it
Answers
Answered by
4
Step-by-step explanation:
A can finish work in 12 days
work done by A in 1 day = 1/12
B can finish work in 15 days
work done by B in 1 day = 1/15
C can finish work in 10 days
work done by C in 1 day = 1/10
work done by all A B C in one day = 1/12 +1/15+1/10
=(5+4+6)/60
15/60
1/4
= 4days
hope this helps you
mark as brainliest
Answered by
0
Answer:
4 days
Step-by-step explanation:
now
in 4 days complete the work