A, B and C can do a piece of work in 15, 12 and 20 days respectively. They started the work together , but C left after 2 days. In how many days will the remaining work be completed by A and B?
Answers
Answered by
2
Answer:
20 days exactly = c left two days while the A and B = 20 days