A, B and C can do a piece of work in 15, 12 and 20 days respectively. They began to work,
but C left after working for 2 days. How many days will be needed to complete the
remaining work?​

Answers

Answered by ashukumar2053
0

Answer:

4 days

Step-by-step explanation:

Work is done by A in one day =

15

1

By B=

12

1

C=

20

1

Together in 1 Day =

15

1

+

12

1

+

20

1

=

60

4+5+3

=

60

12

=

5

1

2 days work =

5

2

Remaining work = 1−

5

2

=

5

3

one day work of A,B ⇒A+B=

15

1

+

12

1

=

60

4+5

=

60

9

=

20

3

(A+B) work for t days =

20

3

t=

5

3

t=4 days

A and B will complete the work in 4 days.