A,B and C can do a piece of work in 16 days, 12 days and 15 days respectively. How long will they take to finish it if they work together
Answers
Answered by
1
Answer:
4 12/17
Step-by-step explanation:
Given,
A,B and C can do a piece of work in 16 days, 12 days and 15 days respectively.
A=1/16
B=1/12
C=1/15
How long will they take to finish it if they work together
A+B+C=1/16+1/12+1/15
=15+20+16/240
=51/240
=17/80
80/17=4 12/17