A, b and c can do a piece of work in 18 days, 27 days and 36 days respectively. they start working together. after working for 4 days. a goes away and b leaves 7 days before the work is finished. only c remains at work from beginning to end. in how many days was the whole work done?
Answers
Given:
A, B and C can do a piece of work in 18 days, 27 days and 36 days respectively.
All 3 work together for 4 days
After 4 days A leaves and B leaves before 7 days the work is finished
To find:
In how many days was the whole work done?
Solution:
So,
In 1 day, the amount of work A will do =
In 1 day, the amount of work B will do =
In 1 day, the amount of work C will do =
∴ The amount of work done by A, B & C together in 4 days is,
=
=
=
=
=
∴ The remaining amount of work to be done after A leaves,
=
=
=
Let "x" be the no. of days when B and C works together.
We know that B leaves 7 days before the work is finished, so C will do the remaining work in 7 days.
Now, we can form the equation as,
[Amount of work done by B and C in x days] + [Amount of work done by C in 7 days] =
⇒
⇒
⇒
⇒
⇒
⇒
⇒
∴ Total no. of days taken to complete the whole work = 4 + 5 + 7 = 16 days
Thus, in 16 days, the whole work was done.
----------------------------------------------------------------------------------------
Also View:
A ,b and c together can do a piece of work in 15 days b alone can do it in 30. days and c alone can do in 40 days in how many days will a alone do the work.
https://brainly.in/question/4535453
A,B and C can together do some work in 72 days. A and B together do two times as much work as C alone, and A and C together can do our times as much word as B alone. Find the time taken by C alone to do the whole work.
https://brainly.in/question/6310684
A,B and C can do a piece of work in 10,9 and 15 days respectively. they started the work together but C left after 2 days. in how many days will the remaining work be completed by A and B?
https://brainly.in/question/4713115