A, B and C can do a piece of work in 20, 20 and 40 days respectively.
They began the work together but C left 2 days before the completion of
work. In how many days would the work have been completed?
Answers
Answer:
11 days
Explanation:
One day's work of A, B and C = (1/24 + 1/30 + 1/40) = 1/10.
C leaves 4 days before completion of the work, which means only A and B work during the last 4 days.
Work done by A and B together in the last 4 days = 4 (1/24 + 1/30) = 3/10.
Remaining Work = 7/10, which was done by A,B and C in the initial number of days.
Number of days required for this initial work = 7 days.
Thus, the total numbers of days required = 4 + 7 = 11 days.
The work can be completed in 8.4 days
Explanation:
Given:
1. A, B and C can do a piece of work in 20,20 and40 days respectively.
2. They began the work together but C left 2 days before the completion of
work
To find:
How many days would the work have been completed
Solution:
==> A can do a work in 20 days
==> B can do a work in 20 days
==> C can do a work in 40 days
==> A's one-day efficiency is
==> B's one-day efficiency is
==> c's one-day efficiency is
==> Let, work done = x
==> A+B+C =
==> Work done by A,B,C = = 1
==> C leaves before 2 days
==> Work done by A,B,C = = 1
==>Solve the equation
==> Work done = = 1
==> Work done = = 1
==> Now, the denominator is the same
==>
==> 2x+2x+x-2 =40
==> 5x-2=40
==> 5x = 40+2
==> 5x = 42
==> x = 42÷ 5
==> x = 8.4 days
==> The work can be completed in 8.4 days