A, b and c can do a piece of work in 30, 45, and 90 days. In how many days can a alone do the work if he is assisted by b and c on every 4th day?
Answers
LCM of 30,45 and 90 is 180
So total work is 180 units
A=180/30=6units/day
B=180/45=4units/day
C=180/90=2units/day
A does the work alone for 3 days
So, for 3 days
A=6units×3=18units
A is assisted by B and C on 4th day,
Therefore total work on 4th day = 6+4+2=12units
Total work done by them in a set of 4 days = 12+18=30 units
Therefore to complete 180 units, 180/30=6 such sets of 4 days are needed.
6 sets of 4 days means 6×4=24 days
Therefore A alone can do the work if he is assisted by B and C on every 4th day in 24 days.
Answer: 24 days
Step-by-step explanation:
- Given A,B and C can do a work in 30,45 and 90 days.
- LCM of 30,45 and 90 is 180.
- So, there is a total of 180 units of work.
- Work done by A in a day=
- Work done by B in a day=
- Work done by B in a day=
- So, in a set of 4 days total work done by A,B and C =(6*4)(4+2)
=24+6
=30 units
- So, to complete 180 units of work number of sets of 4 days required=
=6 units
- Total number of days required=6*4
=24 days
- Hence, the total number of days required is 24 days.
#SPJ2