Math, asked by sakaldeo3032, 11 months ago

A, b and c can do a piece of work in 30, 45, and 90 days. In how many days can a alone do the work if he is assisted by b and c on every 4th day?

Answers

Answered by hnandankp9j7mz
15

LCM of 30,45 and 90 is 180

So total work is 180 units

A=180/30=6units/day

B=180/45=4units/day

C=180/90=2units/day

A does the work alone for 3 days

So, for 3 days

A=6units×3=18units

A is assisted by B and C on 4th day,

Therefore total work on 4th day = 6+4+2=12units

Total work done by them in a set of 4 days = 12+18=30 units

Therefore to complete 180 units, 180/30=6 such sets of 4 days are needed.

6 sets of 4 days means 6×4=24 days

Therefore A alone can do the work if he is assisted by B and C on every 4th day in 24 days.

Answered by VaibhavSR
0

Answer: 24 days

Step-by-step explanation:

  • Given A,B and C can do a work in 30,45 and 90 days.
  • LCM of 30,45 and 90 is 180.
  • So, there is a total of 180 units of work.
  • Work done by A in a day=\frac{180}{30}=6\ units
  • Work done by B in a day=\frac{180}{45}=4\ units
  • Work done by B in a day=\frac{180}{90}=2\ units
  • So, in a set of 4 days total work done by A,B and C =(6*4)(4+2)

                                                                                              =24+6

                                                                                              =30 units

  • So, to complete 180 units of work number of sets of 4 days required=\frac{180}{30}

                      =6 units

  • Total number of days required=6*4

                                                          =24 days

  • Hence, the total number of days required is 24 days.

#SPJ2

Similar questions