A, B, and C can do a piece of work in 36 days, 54 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and left 3 days before the work was completed. For how many days did C work?​

Answers

Answered by vsvermasumit24
0

Answer:

60 days

c worked for

Step-by-step explanation:

total work = 108 units

efficiency of A = 3

" " " B = 2

" " C= 1

they worked together for 9 days

wok done = (3+2+1)×9 = 54units

work left = 54 units +3 days before b left the work so total work = 60

days taken by c = 60 /1 =60