A B and C can do a piece of work in 5 days.A can do the work in 10 days.B can do the work in 12 days.In how many days C do the work?

Answers

Answered by Muskan1101
15
Here's your answer!!

___________________________

(A +B+C )can do piece of work in 5 days.

(A+B+C)'s one day work =
 =  >  \frac{1}{5}

A can of a piece of work in 10 days.
One day work of A =
 =  >  \frac{1}{10}
B can do a piece of work in 12 days
One day work of B =
 =  >  \frac{1}{12}
Let the one day work be C be x

A/q

 =  >  \frac{1}{10} +  \frac{1}{12} + x =  \frac{1}{5}  \\  =  > ( \frac{6 + 5}{60}) + x  =   \frac{1}{5}
 =  >  \frac{11}{60} + x =  \frac{1}{5}   \\  =  > x =  \frac{1}{5}  -  \frac{11}{60}
 =  > x =  \frac{12 - 11}{60}  \\  =  > x =  \frac{1}{16}
Hence,
One day work of C =
 =  >  \frac{1}{60}
And C can complete it in 60 days.

______________________________

Hope it helps you !! :)

Muskan1101: Thanks for brainliest :)
sapna69: awesome dearie ❣️
ayush8957: who are you sapna69
Muskan1101: Thanks dear !!
ayush8957: what dear
Answered by arpan237
1
AB and C can do a peice of work in 1/5 days
A can do a peice of work in 1/10 days
B can do apeice of work in 1/12 days
AB can do a piece of work in 11/60 days
C can do a peice of work in 1/5-11/60
C can do work in 60 days