Math, asked by NikhilRai123, 11 months ago

A,B and C can do a piece of work in 6, 8, and 12 hours respectively. They started the work together and after 1 hour B left the work. In how much time will the remaining work be completed by A and C? Fast! Answer please

Answers

Answered by maliha33
2

Answer:

18 hours because 6+12=18

so a is 6 and c is 12

b have left work after 1hour so 1+6+12=19 hours ok

Answered by perfectok10
0

Answer:

A and C will complete the remaining work in 4 hours.

Step-by-step explanation:

Time taken by A to do the piece of work = 6 hours

Rate at which A can the piece of work / efficiency of A = \frac{1}{6}

Time taken by B to do the piece of work = 8 hours

Rate at which B can the piece of work / efficiency of B = \frac{1}{8}

Time taken by C to do the piece of work = 12 hours

Rate at which C can the piece of work / efficiency of C = \frac{1}{12}

A, B and C worked together for 1 hour.

∴ Amount of work done = Rate at which the work done * Time taken

Since 3 people worked together, the combined rate at which the work  done / combined efficiency =sum of their efficiencies.

So the amount of work they completed in that hour = (\frac{1}{6} + \frac{1}{8} + \frac{1}{12}) * 1

                                                                                      = \frac{3+4+2}{24}

                                                                                      = \frac{9}{24}

                                                                                      = \frac{3}{8}

i.e., \frac{3}{8} of the work was completed when they worked for 1 hour.

--------------------------------------------------------------------------------------------------------------

B left after 1 hour.

Amount of work left to do = 1 - \frac{3}{8}

                                           = \frac{5}{8}

Now, \frac{5}{8} of the work has to be completed by A and C alone.

Combined efficiency of A and C = \frac{1}{6} + \frac{1}{12}

                                                      = \frac{2+1}{12}

                                                      = \frac{3}{12}

                                                      = \frac{1}{4}

Now the time taken for them to complete the work = 1 ÷ their combined efficiency

                                                                                     = \frac{1}{\frac{1}{4} } = 4

∴ The time taken for A and C to complete the remaining work is 4 hours.

Special Thanks to a Brainly Expert @navanithishere.

Similar questions