A, B and C can do a piece of work in 8 days, 12 days and 16 days respectively. How
long will they take to finish. If they work together ?
if you spam I will report your answer
Answers
Answered by
0
Answer:
A and B do (1/8)th of the work in a day.
B and C do (1/12)th of the work in a day.
A and C do (1/16)th of the work in a day.
2A, 2B and 2C do (1/8)+(1/12)+(1/16) = (18/144)+(12/144)+(9/144) = (39/144) or (13/48)th of the work in a day.
Or A, B and C do (13/96)th of the work in a day.
So A, B and C together will complete the whole work in 96/13 or 7 and 5/13th of the 8th day.