A B and C can do a work in 12 15 25 days .After 3 days B left the work In how many days the remaining work will be completed by both A and C together ?​

Answers

Answered by kishangaming699
1

Answer:

x/10 + 3/12 + x/25 = 1

30x + 75 +12x = 300

42x = 225

x = 5 5/14 days

So Total time = 5 5/14 days OR remaining work is done by A & C in 2 5/14 days