Math, asked by anuragkumarSwag2191, 1 year ago

A, b and c can do a work in 15 days. The start together. When work is done a leave the work. Now the work will take 4 days more to be completed. When of the work is done b leave the work. Now the work will take 2 days more to be completed. In how many days c can complete the whole work.

Answers

Answered by autumnr35
0

Answer:

m = 55/5= 11 days.

Step-by-step explanation:

There are multiple ways of doing this :

Method 1

A & B together can complete work in (25x20)/(25+20) =500/45 = 100/9 days.

They complete 5 x 9/100= 9/20 work in 5 days.

Remaining 11/20 work done by B in 11/20 x 20 = 11 days.

Method 2

A works only for 5 days completing 5/25 = 1/5 part of work.

Remaining 4/5 work is done by B in 4/5 x 20 = 16 days.

=> B works for 11 days after A leaves.

Method 3

Let B take m days after A leaves.

Since A & B work together for 5 days, we have :

5/25 + (5 + m)/20 = 1

Taking LCM as 100,

20+ 5(5 + m) = 100

=> 20 + 25 + 5m = 100

5m = 100 - 45 = 55

m = 55/5= 11 days.