A,B and C can do a work in 16 days, 12 4/5 days and 32 days respectively. they started the work together but after 4 days A left .B left the work 3 days before the completion of the work. in how many days was the work completed
Answers
Solution :-
→ LCM of 16 , (64/5) & 32 = 64 units = Let Total work.
So,
→ Efficiency of A = (Total work) / (Total No. of Days.) = (64/16) = 4 units/day.
Similarly,
→ Efficiency of B = (Total work) / (Total No. of Days.) = 64/(64/5) = 5 units/day.
Similarly,
→ Efficiency of C = (Total work) / (Total No. of Days.) = (64/32) = 2 units/day.
then,
→ Efficiency of (A + B + C) = 4 + 5 + 2 = 11 units / day.
so,
→ in first 4 days (A + B + C) completed = 4 * 11 = 44 units of work .
then,
→ Left work to be done = Total work - completed in 4 days = 64 - 44 = 20 units.
Now, Statement :-
- After 4 days A left the work.
- 3 days before the completion of the work B left .
Conclusion :-
- we can conclude that, for last 3 days only C works alone .
so,
→ in last 3 days C done = 3 * 2 = 6 units of work.
therefore,
→ Left work now = 20 - 6 = 14 units.
we can say that, this left work was done by (B + C) .
so,
→ Time taken by (B + C) = 14/(5 + 2) = 14/7 = 2 days.
hence,
→ Total time taken to complete whole work = 4(A + B + C) + 2(B + C) + 3(C) = 4 + 2 + 3 = 9 days. (Ans.)
∴ The work was completed in 9 days.
Learn more :-
Giri does 2/5 piece of work in 10 days. Ankit does 5/9 of the remaining work in 15 days and Gaurav finishes remaining wo...
https://brainly.in/question/21025557
Shivam alone can do a work in 12 days and Maanik alone can do it in, 15 days. Both started the work together and after w...
https://brainly.in/question/14687371