A, B and C can do a work together in a certain number of days. If A leaves after half the work is done, then the work takes 4 more days for completion, but if B leaves after half the work is done, the work takes 5 more days for completion. If A takes 10 more days than B to do the work alone, then in how many days can C alone do the work?
Answers
Answered by
3
Answer:
C alone can do the work in 52.5 days
Step-by-step explanation:
Let B can do the work in x days
then, A can do the work = x + 10 days
In 1 day B does = 1/x work
In 1 day A does = 1/(x+10) work
Let C does work in y days
Then in 1 day C does = 1/y work
Let A, B, C can finish the work in n days
Then
............(a)
A, B, C can finish half work in = n/2 days
According to the question
B and C can do 1/2 work in 4 more days days
Thus
or, ......... (1)
Also
or, ............(2)
Subtracting eq (1) from eq (a) we get
............ (i)
Subtracting eq (2) from eq (a) we get
.................(ii)
From (i) and (ii)
Therefore,
Thus, from eq (1)
Thus, C alone can do the work in 52.5 days
Similar questions