A,B and C can do one work in 10 days and B and C both can do one work in 15 days . In how many days did Only A can do that work alone .
Answers
Answered by
0
A can finish the work in ten days
Answered by
4
Required Answer:-
Given:
- A, B and C can do one work in 10 days.
- B and C can do one work in 15 days.
To find:
- Time taken by A to do the work alone.
Solution:
Let total work be 1.
A, B and C can do one work in 10 days.
➡ One day work of A, B and C will be = 1/10
B and C can do one work in 15 days.
➡ One day work of B and C = 1/15
So,
➡ One day work of A = (One day work of A, B and C) - (One day work of B and C)
= 1/10 - 1/15
= (3 - 2)/30
= 1/30
So, time taken by A to complete the work alone,
= 1 ÷ 1/30
= 30 days.
★ Hence, A alone completes the work in 30 days.
Answer:
- A alone completes the work in 30 days.