A B and C can do the piece of work in 4 days, A alone can do it in 10 days, B alone can it in 18 days, in how many days will C alone do the same work??
Answers
Answer :
C alone can do the same work in 10.59 days.
Step-by-step explanation :
Given :
- A, B and C can do the piece of work in 4 days
- A alone can do it in 10 days
- B alone can it in 18 days
To find :
the number of days taken by C to do the work alone
Solution :
Let "x" be the number of days taken by C to do the work alone.
Work done by C alone in one day = 1/x
A alone can do the work in 10 days :
Work done by A alone in one day = 1/0
B alone can do the work in 18 days :
Work done by B alone in one day = 1/18
A, B and C can do the work together in 4 days :
Work done by them together in one day = 1/4
So,
Work done by them together in one day = Work done by A alone in one day + Work done by B alone in one day + Work done by C alone in one day
Therefore, C alone can do the work in approximately 10.59 days
Step by step explanation:-
Given :-
A,B,C Can do work in 4days
A alone can do in 10days
B alone can do in 18days
To find :-
How many days required for C alone to complete the work
Solution :-
For finding the C alone work We have to find first one day work
Let the work done by C is x
One day work of A is 1/10
One day of B is 1/18
One day work of C is 1/x
One day work of A,B,C is 1/4
So,
Work done by together in one day = Work done by A alone + Work done by B alone + Work done by C alone
So,
= + +
- = +
=
=
=
=
=
=
=
=
x = 10.599
So, work done by C alone is 10.59 days
Hope my answer helps to u