Math, asked by rahuljeettiwari, 7 months ago

A,B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. What is ratio of their one day's work?​

Answers

Answered by tennetiraj86
0

Answer:

answer for the given problem is given

Attachments:
Answered by GRANDxSAMARTH
2

Ratio of their one day's work=> 5 :4 : 3

Ratio  \: of  \: their  \: one \:  day's  \: work \: => \: 5 \:  : \: 4  \: : \:  3