A, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. If all the three work at it together and paid Rs. 960 for the whole work, how much share of money A will get?Required to answer. Single choice.


pls tell write answer its very important for me guys​

Answers

Answered by idiot2006
6

Answer:

A's share = ₹400

Step-by-step explanation:

Time taken to complete the work by :

  • A = 12 days
  • B = 15 days
  • C = 20 days

So , work done by them in a day :

  • A = 1/12
  • B = 1/15
  • C = 1/20

If all three lf them work together then the total work work by them = 1/12 + 1/15 + 1/20 = 1/5

So , days required to complete the work if the they work together = 5/1 = 5 days

Work done by A , B and C = 5/60 , 4/60 and 3/60

So , ratio of their works = 5:4:3

So , A's share = 5/12 × ₹960 = ₹400