Math, asked by singhanavnita8, 10 months ago

A ,B and C can finish a task in 42 days, 84 days and 28 days .A started the work ,B joined them after 3 days, if C joined them after 52 days from beginning ,then for how many days did A work till the completion​

Answers

Answered by ambarkumar1
1

Let the task be x

A can finish a task in 42 days

Task done by A in 1 day = x / 42

B can finish a task in 84 days

Task done by B in 1 day = x / 84

C can finish a task in 28 days

Task done by C in 1 day = x/28

Now

According to question

A started the work ,B joined them after 3 days,

(x/42) × 3 = x / 14. – (1)

if C joined them after 52 days from beginning. This means A and B together did the work for 52 3 days = 49 days

[ ( x / 42 ) + ( x / 84 ) ] × 49

= [ ( 2x + x) / 84 ] × 49

= ( 3x / 84 ) ×49

= (49 x / 28)

= 7x / 4 – ( 2 )

Now let the no of remaining days be y

In this remaining days all of them did the work collectively.

Hence,

( x/ 42 + x/84 + x/28 ) × y

= [ ( 2x + x + 3x) / 84 ] × y

= [ 6x / 84 ] × y

= x/14 × y

= xy/14. – ( 3 )

Adding 1, 2 amd 3

( x / 14 ) + ( 7x / 4 ) + ( xy / 14 ) = x

{Since total work is x }

( 1/14 + 7/4 + y/14 ) = 1

2+49+2y = 1 × 28

51 +2y = 28

2y = 28 – 51

Sorry my answer is coming wrong but i think this should be the approach.

Sorry once again :(

Similar questions