Math, asked by lakshmanrajr, 5 months ago

A, B and C can finish a work in 10, 12
and 15 days respectively. If B stops
after 2 days, how long would it takes for A and C to complete the work ?
(A) 3 days
(B) 5 days
(C) 7 days
(D) 10 days​

Answers

Answered by PratikLilhare
1

Answer:

5 days

Step-by-step explanation:

A can complete 1/10 work in 1 day

B can complete 1/12 work in 1 day

C can complete 1/15 work in 1 day

B work for 2 days only so he does 2/12 work

let the days taken by A and C be x

so,

x(1/10 + 1/15) + 2/12 = 1

x = 5 days

Answered by Anonymous
1

Answer:

OPTION NO. (B) IS CORRECT = 5