A, B, and C can together do some work in 72 days. A and B can together do two times as much work as Calone and
A and C together can do four times as much work as B alone. Find the time taken by C alone to do the whole work
Answers
Answered by
3
the work done by A, B and C together
A + B + C =>72 days ------(1)
A + B =2C ---------(2)
A + C = 4B -----------(3)
subtitute (2) in (1) we get
2C + C => 72 means that three C can do that work in 72 days
so one C take 72 x 3 days ie. 216 days