A, B and C complete a certain work in 6, 8 and 12 days respectively. In how many days would all of them complete the work if they work together?

pls answer with statements​

Answers

Answered by sanketdewase
0

Answer:

2 + 2/3 days

Step-by-step explanation:

consider total work as lcm of 6,8,12 days i.e. 24

efficiency of A = 24/6 = 4 unit / day

efficiency of B = 24/ 8 = 3 unit / day

efficiency of C = 24/12 = 2 unit/day

from above total work done by A, B, C together

= 4+3+2= 9unit /day

therefore total days required

= 24/9

= (2+6/9)days

= (2+2/3) days