Math, asked by abhi6117, 1 year ago

A, B and C do a piece of work in 15, 12 and 20 days respectively.they started the work together ,but C left after 2 days. In how many days will the remaining work be completed by A and B

Answers

Answered by shantanurauthan
3

A         B           C

15       12          20

LCM(15,12,20) = Total Work

                      =  60

                                         A         B           C

                                         15       12          20

Work done in 1 day          4        5            3

Work done by all three in 1 day = A + B + C = 4 + 5 +3 = 12

C left after 2 days

Therefore work done in 2 days  = 2 * (A+B+C) = 24

Remaining work = 60 - 24 = 36

This remaining work has to done by A and B because C has left

Work done by A + B in 1 day = 9

Number of days = 36/9 = 4 days

                                                   