A, b and c, each of them working alone can complete a job in 6, 8 and 12 days respectively. if all three of them work together to complete a job and earn rs.2340, what ill be c's share of the earnings?

Answers

Answered by TooFree
11

A can complete the work in 6 days

⇒ 1 day = 1/6 of the work


B can complete the work in 8 days

⇒ 1 day = 1/8 of the work


C can complete the work in 12 days

⇒ 1 day = 1/12 of the work


Find their ratio:

Ratio of A : B : C = 1/6 : 1/8 : 1/12

Multiply by 24 through:

Ratio of A : B : C = 4 : 3 : 2


Solve x:

Ratio of A : B : C = 4x : 3x : 2x

4x + 3x + 2x = 2340

9x = 2340

x = 260


Find each of their share:

A = 4x = 4(260) = Rs 1040

B = 3x = 3(260) = Rs780

C = 2x = 2(260) = Rs 520


Answer: C's share is Rs 520