A,B and C finish a work in 15 days , 20 days and 25 days . If all the three work for a day each in turn , then on which day the work will be completed?
Answers
Answered by
0
Answer:
300/47days
6(18/47)
Step-by-step explanation:
he will take 6 whole days&18/47 of another day
Similar questions