A,B and C individually can do a work in 10 days. 12 days and 15 days respectively. If they start working together. then the number of days required to finish the work is ?
Answers
Answered by
1
Answer:
Assume, Total Work = 1
therefore,
A's work in 1 day= 1/10
B's work in 1day= 1/12
C's work in 1day = 1/15
A, B, C together in one day =
1/10 + 1/12+ 1/15
= (6+ 5+ 4) / 60
=15/60
= 1/4
A,B, C together will finish the work in,
1÷ 1/4
= 1× 4/1
= 4days
Step-by-step explanation:
Find the LCM of 10, 12,15.
If together they can do one-fourth of the work in 1 day,
then two-fourth in two days, three-fourth in 3 days and four-fourth (4/4=1) in 4 days.