A, B and C take 3 days, 4 days and 6 days respectively to complete a work. How long will they
take to complete the work, if they work together?
Answers
Answered by
2
Answer:
4
Step-by-step explanation:
1/3+1/4+1/6
4+3+2/12
9/12
3/4
4days