A, B and C take 3 days, 4 days and 6 days respectively to complete a work. How long will together?
Answers
Answered by
55
Answer:
⚠ _ Hello _ ⚠
Step-by-step explanation:
⚫ Solution ⤵
1 Day work of A =>
1/3
1 day work of B =>
1/4
1 Day work of C =>
1/6
➡ If they work together
1/3 + 1/4 + 1/6
➡ 4 + 3 + 2/12
➡ 9/12
Thus, they will work together in 12/9 days = 4/3 days
⭐⭐ Have a great day⭐⭐
Answered by
0
Answer:
one day work of a is equal to 1 upon 3 one day work of physical to 1 upon 4 oneday work of c is equal to one can see if they work together 1 upon 3 + 1 upon 1 + 1 upon 6 is equal to 9 UP board 12 is equal to 3 upon 4 is the answer