Math, asked by av508467, 2 months ago

A. B and C together can complete a work in 4 days. They started the work together but after 2 days A left the
work. B and C together completed the remaining work in three days. In how many days, can A alone
complete the whole work?​

Answers

Answered by araj3024
0

Answer:

and C together can complete a work in 4 days. They started the work together but after 2 days A left the

work. B and C together completed the remaining work in three days. In how many days, can A alone

complete the whole