a, b and c together can do a piece of work in 15 days B alone can do it in 30 days and C alone can do it in 40 days in how many days will a alone do the work
Answers
Answered by
6
Given,
(A+B+C) can do a piece of work in = 15 days
(A+B+C)’s 1 day work = 1/15
B alone can do a piece of work in = 30 days
B’s 1 day work = 1/30
C alone can do a piece of work in = 40 days
C’s 1 day work = 1/40
So,
A’s 1 day work = 1/15 - 1/30 + 1/40
= 1/15 - 4+3/120
1/15 - 7/120
8−7 /120
= 1/120
∴ A can do a piece of work in 120 days.