A, B and C together can do a piece of work in 4 days. A alone can do the same work in 12 days and B alone can do the same work in 10 days. How long will C take to do the work alone?
Answers
Answered by
0
Step-by-step explanation:
In this question we divide the work done by a man in 1 day,
since the work is done by all three men in 4 days, so we can say that they are doing 1/4 of work in one day,
also, A and B can do the same work in 12 and 10 days respectively,
therefore work done by A and B in 1 day is 1/12 and 1/10 respectively.
let C take x days to complete the work alone, that is he does 1/x work in 1 day
summing up our conclusion :
work done by (A+B+C) in 1 day = 1/4
1/12 + 1/10 + 1/x = 1/4
1/x = 1/15
therefore C takes 15 days to complete the work alone.