Math, asked by hanisha40, 1 year ago

a b and c together can do a piece of work in 40 days after working with B and C for 16 days a leaves and then B and C complete the remaining work in 40 days more a alone can do the work in?​

Answers

Answered by Strangercitizen1525
6

Answer:

Step-by-step explanation:

Work done by A,B,C in 1 day = 1/40

Work done by A,B,C in 16 days

= 16/40 =2/5

Remaining work = 1 - 2/5

=3/5

.

This remaining work 3/ 5

is completed by B and C in 40 days.

Therefore work done by B and C in 1 day =(3/5) / 40 =3/ 200

Work done by A in 1 day

=1/40 − 3/200

= 1 /100

Therefore A alone can finish the work in 100 days.

hope it helps..