A, B and C together complete a piece of work in 15 days. A and B complete the work in 20 days. A and C do the
same work in 30 days. In how many days, will
(1) B alone?
(ii) C alone? (iii) B and C together, complete the work?
Answers
Answered by
0
Answer:
B = 90-60X
Step-by-step explanation:
X= 283
Answered by
1
Step-by-step explanation:
A B C completes 1/15 work in 1 day
A B complete 1/20 work in 1 day
A C complete 1/30 work in 1 day
Days B alone need to complete work= 1/15 - 1/30
= 2/30= 1/15= 15 days
Days C alone needs to complete work= 1/15- 1/20
= 4-3/60= 1/60 = 60 days
Days B and C together needs= 1/ 15+1/60 = 4/60
= 1/15 or 15 days ans