Math, asked by MadElectorate, 5 days ago

A, B and C together complete a piece of work in 4 days. B alone can do it in 18 days , while C alone
takes 9 days to do it , then A alone will do it in how many days?

Answers

Answered by bhanuprakashreddy696
1

Answer:

12 days required to do work