Math, asked by abhipsa386, 10 months ago

A. B and C together finish a work in 4 days. If A alone can finish the same work in 8 days and B in 2 days ,find how long will C take to finishthe work.​

Answers

Answered by nainatalwekar
1

Answer:

C take 9 days to fish his work

Similar questions