Math, asked by triptigupta504, 5 months ago

A, B and C working together can plough a field in 24/5 days.A and C together can do it in 8 days.How long would B working alone take to plough the field​

Answers

Answered by prasanthikuchipudi
2

Answer:

12 days

Step-by-step explanation:

A+B+C=5/24 days eq(1)

A+C= 1/8 days eq(2)

by substituting eq(2) in eq(1)

we get B=12 days