A,B andC can do a piece of work in 20,30 and 60 fays rrspectively.In how many days can A do the work if he is assisted
Answers
Answered by
0
Answer:
I don't understand rrispectivaly
Step-by-step explanation:
7
Answered by
2
Answer:
Step-by-step explanation:
A's 2 days's work=(1/20)*2=1/10
A+B+C 's 1 day work=(1/20+1/30+1/60)=1/10
work done in 3 days=(1/10+1/10)=1/5
now 1/5 work done in 3 days
whole work=3*5=15 days